Extradosed bridge across the Nosicka dam alongside Puchov - structural design, Slovakia

Extradosed bridge across the Nosicka dam alongside Puchov - structural design, Slovakia

design of construction methods, static calculations, shop drawings for bridge substructure and superstructure

More information

The Old Bridge over the Danube River in Bratislava

The Old Bridge over the Danube River in Bratislava

the concept and project for removal of the bridge, processing of technological procedures

More information

Bridge on the D35 across the railway station near Uhersko - built by rotating

Bridge on the D35 across the railway station near Uhersko - built by rotating

TRECOL SYSTEM support-technology for rotating of two bridge box girders 87 m long, each with weight 4.500 ton

More information

Bridge 204-00 on the D1 highway Hričovské Podhradie – Lietavská Lúčka, Slovak Republic

providing of TRECOL SYSTEM for temporary support of parts of main girder during assembling of MSS, Doprastav a.s.

Project name:   D1 HRIČOVSKÉ PODHRADIE – LIETAVSKÁ LÚČKA HIGHWAY, BRIDGE 204-00,
Contractor:  Doprastav a.s.
Position of LKM Consult:   Subcontractor of TRECOL SYSTEM supports
Termination:   project is currently under construction

Project Description

The bridge 204-00 on D1 highway with spans 41m + 5×59m + 41 m, overall length 377 m and depth 33 m above terrain is constructed using movable scaffolding system (MSS) designed by Strukturas. For assembling of MSS main girders in first end span were used three lower TRECOL supports and one higher TRECOL support.

LKM Consult delivery

  • conceptual design of MSS temporary supports in first span of the bridge
  • technical support on construction site
  • subcontractor of TRECOL SYSTEM supports