Extradosed bridge across the Nosicka dam alongside Puchov - structural design, Slovakia

Extradosed bridge across the Nosicka dam alongside Puchov - structural design, Slovakia

design of construction methods, static calculations, shop drawings for bridge substructure and superstructure

More information

The Old Bridge over the Danube River in Bratislava

The Old Bridge over the Danube River in Bratislava

the concept and project for removal of the bridge, processing of technological procedures

More information

Bridge on the D35 across the railway station near Uhersko - built by rotating

Bridge on the D35 across the railway station near Uhersko - built by rotating

TRECOL SYSTEM support-technology for rotating of two bridge box girders 87 m long, each with weight 4.500 ton

More information

Bridge 202-00 on D1 highway Fričovce – Svinia, Slovak Republic

construction work on rectification of bridge bearings on abutments, Eurovia CS a.s.

Project name: Diaľnica D1 Fričovce–Svinia, objekt 202-00 Most nad cestou III/018 189 a Štefanovským potokom v km 80,5 D1
Contractor: Eurovia CS a.s.
Position of LKM Consult: conceptual design of rectification and bearing replacement, elaboration of technical documentation, leading of construction process on site
Termination: 21.7.2015

Project Description

Bridge 202-00 has four spans 37,3 +2×45,0 +39,8 m. Total width of superstructure is 29,5 m, because bridge carries whole highway profile using one superstructure in depth 37,12 meters above terrain. Cross-section compound of 8,30 m wide concrete box girder with shallow struts supporting post-concreted composite slab. Construction depth of box girder is 2,69 m. Superstructure is connected to substructure using frame connections on piers and pot bearings on abutments.

During construction occurred abnormal settlement, movement and inclination of both abutments.

LKM Consult delivery:

  • conceptual design of rectification and bearing replacement
  • elaboration of technical documentation
  • leading of construction process on site

Firstly were installed anchors into bottom part of each abutment. These anchors were designed to carry possible transversal forces, which are usually taken by one-directional bearing on abutment.

On abutment OP5 was bridge superstructure lifted using hydraulics by force 11200 kN.  Then were inserted two rectification plates (thicknesses 25 mm and 20 mm) into area between upper anchor plate and sliding plate of pot bearing. New longer bolts were mounted and finally superstructure was dropped into bearings.

On abutment OP1 was bridge superstructure lifted using hydraulics by force 9800 kN.  Then were dismantled existing sliding plates on both bearings, mounted new sliding plates and longer bolts. In the end of process superstructure was dropped into bearings.

Construction work was complicated by limited access from above into area of abutment.